Sewage sent to the BWRP goes through several steps in the treatment process.
Barscreens
Barscreens remove large solids that are sent into a grinder. All solids are then dumped into a sewer pipe and sent to the City of Los Angeles’ Hyperion Treatment Plant.
Primary Settling Tanks
Readily settable and floatable solids are removed from the wastewater. These solids are skimmed from the top and bottom of the tanks and sent to the Hyperion Treatment Plant.
Secondary Treatment
The wastewater is cleaned through a biological treatment method that uses microorganisms or tiny bugs. Air bubbles up to keep the organisms suspended and to supply oxygen to the bugs so they can metabolize the food, convert it to energy, CO2, and water, and reproduce more microorganisms. The bugs also help to remove ammonia through a complex series of reactions.
Secondary Settling Tanks
The force of the flow slows down as sewage enters these tanks, allowing the microorganisms to settle to the bottom. As they settle, other small particles suspended in the water are picked up, leaving behind clear wastewater. Some of the microorganisms that settle to the bottom are returned to the system to be used again, while the excess microorganisms are washed out.
Tertiary Treatment
Seven deep-bed, single-media, gravity sand filters receive water from the secondary basins and filter out the remaining solids. As this is the final process to remove solids, the water in these filters is almost completely clear.
Chlorine Contact Tanks
Three chlorine contact tanks disinfect the water to decrease the risks associated with discharging wastewater containing human pathogens. This step protects the quality of the waters that receive the wastewater discharge.
Reclaimed Water Pump Station
The pump station distributes reclaimed water to users around the City. Of the 330 million gallons of reclaimed water distributed over the last year, 50% was used for the cooling tower at the Burbank Water and Power steam power plant, 30% was used at Debell golf course, 10% was used at the City of Burbank Landfill, and 10% went to other uses.